SAM - Chapter 4900

4941     OVERVIEW 
(Revised 6/03)

Once the FSR for an information technology project has been approved the project may proceed, contingent upon any conditions imposed by Finance. Throughout the project phases, agency management must follow the IT Project Oversight Framework (see SIMM Section45) to provide the appropriate level of independent project oversight, project management practices and project risk assessments to ensure the success of the project. 

Post-Implementation and Evaluation Report. Following completion of each information technology project, a post-implementation evaluation must be carried out by the agency. The evaluation should:
  1. Measure the benefits and costs of a newly-implemented information technology application or system against the most recently approved project objectives; and
  2. Document projected operations and maintenance costs over the life of the application or system.

 